Innisfail Harbour Pile Rehabilitation

CLIENT: Cassowary Coast Regional Council

DATE OF COMPLETION: August 2019

EQUIPMENT: Piling Barge

WORK SCOPE:

 – The fabrication of 20 mooring piles and walkway brackets at our fabrication yard

 – Sand Blasting and Coating of the Piles using a Marine Epoxy

 – Transportation of piles and marine-based machinery to Innisfail from the Sunshine Coast

 – Removal of the existing pile paraphernalia and walkways

 – Alterations, refabrication, and Hot Dip Galvanising of existing walkways

 – Sleeving old 406 dia mooring piles with newly fabricated 508 dia using Nabis Piling Barge

 – Grouting the annulus between the existing mooring piles and the newly fabricated sleeves

Talk to us about marine civil works projects, and see how Nautique can deliver marine dredging near you.

20191001_105249.jpg

Innisfail Harbour Pile Rehabilitation

CLIENT: Cassowary Coast Regional Council

DATE OF COMPLETION: August 2019

EQUIPMENT:

WORK SCOPE:

 – The fabrication of 20 mooring piles and walkway brackets at the Nabis Fabrication Yard

 – Sand Blasting and Coating of the Piles using a Marine Epoxy

 – Transportation of piles and marine-based machinery to Innisfail from the Sunshine Coast

 – Removal of the existing pile paraphernalia and walkways

 – Alterations, refabrication, and Hot Dip Galvanising of existing walkways

 – Sleeving old 406 dia mooring piles with newly fabricated 508 dia using Nabis Piling Barge

 – Grouting the annulus between the existing mooring piles and the newly fabricated sleeves

Alternative initiative conducted by Nautique/Nabis:

 – The prescribed timber fenders were superseded by the use of a combination of Wagner’s CFT and recycled plastic as the external rubbing strips. This option provided an enhanced design life and a long term cost-effective solution. 

​